Smarter Bidding ProgrammeSelecting and implementing a modern bid & pipeline platform, live by end of September
Section 17 / 22
Export full PDF

Team & Resourcing

Small core team, vendor-heavy build, RACI ready

Small core team, vendor-heavy build. Bulgaria bid team lead is a member of the squad, not just a stakeholder. Sized for the ~£250k envelope and a 13-week critical path.

Total effort

8.5 FTE

Peak across 13 weeks

Internal

2.4

28%

Contractor

3.1

36%

Vendor

3.0

35%

Squad mix

Roles by squad

Programme · 2.1 FTEBid Team · 0.4 FTEData · 1.0 FTEVendor · 3.0 FTEIT · 0.5 FTEGovernance · 0.1 FTEChange · 1.1 FTERollout · 0.3 FTE

13-week Gantt

When each role starts and stops

Hover any bar for the role's remit. Click to jump to the section they contribute most to.

Bar colours

Programme· PM, sponsor, oversight
Bid Team· Bulgaria bid team engagement
Data· Migration & data quality
Vendor· Selected platform vendor build
IT· Integrations & SSO
Governance· DPO, GDPR, controls
Change· Training & adoption
Rollout· 14 country leads
Lane = the row label on the left (role · squad · source · fte)
Click any role's bar to open the section that squad contributes to
Role · Squad · Source · FTE
Requirements & vendor · D1Build & migrate · D32Go-live & rollout · D7930 Sep
Project Manager (me)Programme · Internal · 1.0 FTE
D1–D91
Executive SponsorProgramme · Internal · 0.1 FTE
D1–D91
Bulgaria Bid Team LeadBid Team · Internal · 0.4 FTE
D1–D91
Business AnalystProgramme · Contractor · 1.0 FTE
D1–D80
Data Migration LeadData · Contractor · 1.0 FTE
D20–D91
Vendor Delivery LeadVendor · Vendor · 1.0 FTE
D30–D91
Vendor Engineers (×2)Vendor · Vendor · 2.0 FTE
D32–D88
IT / Integration LeadIT · Internal · 0.5 FTE
D20–D88
DPO / Data ProtectionGovernance · Internal · 0.1 FTE
D5–D91
Change & Adoption LeadChange · Contractor · 0.6 FTE
D40–D91
Trainer / EnablementChange · Contractor · 0.5 FTE
D60–D91
Country Leads (14)Rollout · Internal · 0.3 FTE
D60–D91

RACI

Decision rights across the team

Filter by decision, squad or RACI letter. Responsible · Accountable · Consulted · Informed.

Decision

Squad

Highlight

R
Responsible
does the work
A
Accountable
answers for it
C
Consulted
two-way input
I
Informed
kept in the loop
RoleRequirementsVendor selectionConfigurationData migrationAdoption in BulgariaGo-live (30 Sep)14-country rollout plan
Project Manager (me)
Programme
AAAAAAA
Executive Sponsor
Programme
AAICCAA
Bulgaria Bid Team Lead
Bid Team
RCCARCC
Business Analyst
Programme
RCRRCCC
Data Migration Lead
Data
IICRCCC
Vendor Delivery Lead
Vendor
ICRCCRC
Vendor Engineers (×2)
Vendor
IIRCIRI
IT / Integration Lead
IT
ICCCIRI
DPO / Data Protection
Governance
IIICICI
Change & Adoption Lead
Change
IICCRCR
Trainer / Enablement
Change
IIIIRCC
Country Leads (14)
Rollout
IIICIIR