Smarter Bidding ProgrammeSelecting and implementing a modern bid & pipeline platform, live by end of September
Section 08 / 22
Export full PDF

Post-Go-Live Rollout Roadmap

Bulgaria base, then 14 countries in phased waves

15-month view

Bulgaria first, then 14 countries in three waves

Click any phase to explore the workstreams. Milestones are the executive checkpoints on the wall.

Programme Gantt

From Sep go-live to full 14-country coverage

Hover any bar for the workstreams in that phase. Click to jump to the proof section.

Bar colours

Bulgaria go-live· Sep
Wave 1 · 3 markets· Oct–Nov
Wave 2 · 5 markets· Dec–Feb
Wave 3 · 6 markets· Mar–May
Optimise & scale· Jun–Dec+
Lane = the row label on the left (programme phase)
Milestone marker
Click a bar to open its proof section · click a milestone to open its evidence
Programme phase
SepDecMarJunSep+1
Bulgaria go-liveSep
M3
Wave 1 · 3 marketsOct–Nov
M4–M5
Wave 2 · 5 marketsDec–Feb
M6–M8
Wave 3 · 6 marketsMar–May
M9–M11
Optimise & scaleJun–Dec+
M12–M15
Bulgaria base team live
Hypercare
Excel workbooks locked
Adoption dashboard

Programme milestones

Eight executive checkpoints

M1

Bulgaria go-live (30 Sep)

M2

Wave 1 markets live

M3

Group reporting single source of truth

M4

Wave 2 markets live

M5

Wave 3 markets live

M6

All 14 countries live

M7

12-month adoption review

M8

Year-1 win-rate uplift review